The project reached 100% progress and was officially dispatched to the designated site on February 18, 2026.
Project Overview and Milestones
The fabrication process followed a rigorous quality control and technical workflow to ensure all components met the high standards required for GBCPP operations.
Key Technical Details:
- Project ID: POIND-0075-00202.
- Components: 3 Pipe Spools, 2 Flange FFW, and Studbolts.
Fabrication Timeline and Progress:
The project moved through several critical phases throughout February 2026:
- Early February: Material receipt, inspection, and the commencement of fit-up and welding (Progress 14% – 20%).
- Technical Precision: On February 4th, a technical query regarding a 204 mm dimension was resolved with a “Fitting to Fitting” (FTF) actual dimension of 195 mm.
- Mid-February: Completion of welding layer caps, acceptable NDT (Non-Destructive Testing) results, and successful Hydrotests (Progress 60% – 78%).
- Surface Treatment: Rigorous blasting and coating procedures, including premier, second, and top coats with DFT (Dry Film Thickness) verification.
- Completion: Final packaging and delivery on February 18, 2026.