Condensate Tank Repair and Fabrication
After the repairs, a 20-ton load test was conducted on September 3, 2025, using a 45-ton capacity mobile telescopic crane. Non-destructive tests, specifically Magnetic Particle Inspection (MPI) and Dye Penetrant Test, were performed on the pad eyes, critical skid, master link, shackle, and ferrule thimble eyes on both ends of the wire rope sling. The project was completed safely, and the condensate tank was successfully returned to Harbour Energy in Gajah Baru, Natuna.