Boat Landing Installation at WLWP FPSO Anoa Hub And Westlobe Wellhead Platform Harbour Energy, Natuna

On May 29, 2024, PT. Gearindo Prakarsa successfully completed the boat landing installation at the Wellhead Platform (WLWP) location through contract No. 21130005-0B with the title Provision of Material and Services for Offshore Fabrication, Maintenance, and Modification at Anoa Field (FPSO, Anoa Hub, and Westlobe Wellhead Platform). This project involved seven key personnel, consisting of three riggers/scaffolders, three Rope Access Technicians (RAT), and one fitter, who worked with great dedication to ensure the success of this project.

Fabrication by PT. Gearindo

The fabrication of this landing boat was carried out by PT. Gearindo Prakarsa, the trusted partner in this project. The boat landing structure has a load of up to 10 tons, indicating the quality and durability of the materials used in the manufacture and the installation process which was carried out very carefully.

BLI2
BLI3

High Teamwork and Expertise

During the installation process, teamwork and technical expertise of the workers is mandatory. The riggers and scaffolders are responsible for ensuring the scaffolding structure is sturdy and safe, while the Rope Access Technicians carry out installation tasks in hard-to-reach places with special equipment. Our fitters also play a crucial role in the final adjustment and tightening of the structure.

Safety as Top Priority​

Safety is the top priority during this installation process. All personnel involved follow strict safety procedures and comply with all applicable operational standards. As a result, the installation was successfully completed without incident or accident, indicating our company’s commitment to work safety in the field.

BLI4
BLI5